Nyandarua

    1. Major Flagship Infrastructure
    • Olkalou Town Sewerage Project:
      • Status: 100% complete and was officially commissioned by H.E. the President in January 2024.
      • Scope: A Ksh 589.9 Million investment featuring a 3,300m³/day wastewater treatment plant, trunk, secondary, and tertiary sewers, and a public sanitation block.
      • Impact: The system is operational with 458 initial connections and is designed to serve a projected population of 68,800 by 2040.
    • Olkalou Town Sewerage Last Mile Connectivity (LMC):
      • Status: Currently being repackaged for tendering under the National Urban Water Program Phase 1.
      • Scope: A Ksh 533 Million project to add 11km of sewer lines and 500 new connections. It includes a water component to supply an additional 1,000m³/day to the town.
    • Pesi Dam Water Project:
      • Status: Identified as a Vision 2030 priority and recommended for Public-Private Partnership (PPP) funding.
      • Scope: A16-million-cubic-meter capacity dam with a 60m height.
      • Impact: Designed to provide domestic and industrial water to 150,000 households.

Nyandarua has seen the completion of over 40 community water and health-facility-focused projects.

No.

Project Name

Scope of Works

Sub-County

Beneficiaries

1

Kagongo BH Water Supply

Drilling, equipping & civil works

Kinangop

2,500

2

Matundura Pri. Sch. LMC

Trenching and 8km pipelaying

Kinangop

2,000

3

Nyandarua GK Prison

50m³ Masonry Tank construction

Ol Joro Orok

5,000

4

Kianjata Borehole

Equipping and civil works

Ol Joro Orok

2,500

5

Mayu Borehole LMC

13km pipeline extension

N/Nyandarua

1,800

6

Kibathi Pri. Sch. BH

LMC and 2No. storage tanks

Ndaragwa

4,000

7

Thitai Borehole

Drilling and capping

Ol Kalou

2,500

8

Manyatta Borehole

Drilling and capping

Ol Kalou

2,450

9

Nganoini Borehole

Equipping and water kiosk

Nyandarua

2,800

10

Leshau-Karagoini Rehab

LMC for 15,000 beneficiaries

Nyandarua

15,000

11

Muhonia-Turasha Project

LMC for 6,000 beneficiaries

Nyandarua

6,000

12

Gathara Water Pan

12,500m³ pan excavation

Nyandarua

1,500

13

Gichaka Community Pan

10,772m³ pan excavation

Nyandarua

1,100

14

Weru Primary Sch. BH

Drilling, equipping & civil works

Nyandarua

1,500

15

Uhuru Springs Project

50m³ tank and LMC

Nyandarua

3,500

16

JM Village Borehole

Drilling, equipping & civil works

Nyandarua

2,000

17

Bamboo/Heni/Kaugi Rehab

Rehabilitation and diagnosis

Nyandarua

2,000

(Note: Total completed community projects in Nyandarua now exceed 42)

No.

Project Name

Progress Status

Sub-County

Remarks

1

Kiamaiko Borehole

100% (Drilling)

Ndaragwa

Requires equipping/civil

2

Gachicio BH LMC

90%

Kinangop

Extra works ongoing

3

Baari Water Project

10%

Ndaragwa

Slow progress; contractor issues

4

Siambara BH

Design Phase

Ndaragwa

Designed for equipping

5

Gichigirira Borehole

Planning

Kipipiri

Sourcing defloridation units

6

Kahuho Secondary BH

Planning

Ndaragwa

Site resiting in progress

    1. Future Planning & Proposed Projects
    • National Urban Phase II: Proposed projects include the Kipipiri Schemes Water Supply and the Kirima and Kamwana Water Supply.
    • Priority PPP Dams: Kinja Dam is prioritized with a 3 MCM capacity to serve 20,000 households (Ksh 4.0B).
    • Proposed Sewerage Systems: Planning is underway for systems in Njabini Town (Ksh 700M) and Mairo Inya Town (Ksh 800M).
    • Strategic Studies: Clusters identified for feasibility include Engineer-Upper Chania-Murungaru, Mirangine-Ndundori-Lanet, and the Gatimu-Gwa Kiongo Dam-Ndaragwa lines.