Baringo
Major Flagship Infrastructure
• Chemususu Dam Water Supply Project: The project has reached an overall completion status of 98%. Civil works for the treatment plant and the main 5,000m³ reservoir at Baringo High School are completed. Outstanding works include pressure testing 150km of pipeline and the procurement of operational equipment (excavators and billing software). It serves 300,000 people across Eldama Ravine, Mogotio, and Nakuru.
• Kirandich Dam Phase II Water Supply Project: Serving Kabarnet Town, this project is currently at 41% overall physical progress. Key components include:
o Water Supply Works: 60% complete.
o Sewerage System: 31% complete.
o Reservoir Protection from Siltation: 77% complete.
o Management Office Rehabilitation: 33% complete.
• Eldama Ravine Sewerage Project: This National Urban Program project is in the tendering and documentation repackaging phase. It is designed to serve 57,563 people with a 53km sewerage network.
No. | Project Name | Scope of Works | Sub-County | Beneficiaries |
40 | Chemususu LMC (Mogotio Lot 1) | · 108m³ steel tank; 48.1km pipeline | Mogotio | 12,500 |
41 | Chemususu LMC (Mogotio Lot 2) | · 2No. 100m³ tanks; 25.6km pipeline | Mogotio | 8,000 |
42 | Chemususu LMC (E/Ravine Lot 1) | · Masonry tank; 38.1km pipeline | Eldama Ravine | 15,000 |
43 | Chemususu LMC (E/Ravine Lot 2) | · 50m³ elevated tank; 32km pipeline | Eldama Ravine | 12,000 |
44 | Bekibon Water Supply | · Intake, weir, sump, 100m³ tank | Baringo South | 3,500 |
45 | Tian Borehole | · Equipping and civil works | Mogotio | 3,500 |
46 | Katabwa Water Project | · Intake weir, pipeline, masonry tank | Mogotio | 4,000 |
47 | Kaptirgen (JICA) Project | · BH rehab & Kamweton pipeline extension | Baringo North | 2,500 |
48 | Tangulbei Water Pan | · 18,000m³ water pan construction | Tiaty | 3,000 |
49 | Cheploch Water Pan | · 15,000m³ water pan construction | Baringo South | 2,500 |
50 | Kataron Water Pan | · Construction of water pan | Baringo North | 3,500 |
51 | Kositei Water Pan | · Construction of water pan | Baringo South | 3,000 |
52 | Muchukwo WP | · Equipping and civil works | Majimoto | 3,500 |
53 | Kipteweret WP | · Equipping and civil works | Bartabwa | 2,500 |
54 | Kapsok Borehole | · Diagnosis and rehabilitation | Mogotio | 2,000 |
55 | Kabarnet Boys BH | · Equipping and civil works | Baringo Central | 2,000 |
56 | Kaptiegan WP | · Last Mile Connectivity (LMC) | Eldama Ravine | 3,000 |
57 | Kaptana LMC | · Last Mile Connectivity (LMC) | Eldama Ravine | 3,000 |
58 | Simotwe LMC | · Last Mile Connectivity (LMC) | Eldama Ravine | 3,000 |
59 | Kipsogon-Logiri | · Last Mile Connectivity (LMC) | Mogotio | 3,000 |
60 | Ramacha Borehole | · Drilling and capping | Baringo | 1,500 |
1 | Civil works for reinstatement of Kabulyot water project | · Rehabilitation of the existing pipeline network | Baringo | 3000 |
2 | Civil works for oldebes water project | · Tank construction and Conveyance system | Baringo | 1500 |
3 | Construction works for Soibei community water project |
| Baringo | 300 |
4 | Completion of Tugumoi-Tinonei and Chepnyogoson water project |
| Baringo | 570 |
5 | Kimotony water pan | · Excavation and Earthworks. | Baringo | 2000 |
6 | Mochongoi water project | · Construction of intake works, Gravity main, rising main, 50m3 and 100m3 masonry tanks, pump house, solarisation, and Fencing | Baringo South | 3000 |
7 | Solarization of Ndabibi borehole | · Solar Equipping | Mogotio | 2000 |
8 | Solar equipping of olkokwe community borehole | · Solarization of borehole | Mogotio | 700 |
9 | Tuiseru borehole | · Drilling and test pumping.installation of pumping system and solar equipment. Construction of water kiosk with 10m3 plastic tank. Constructiojn of cattle trough. Pipework and fitting. Fencing and gate | Mogotio | 600 |
10 | Boito Secondary School Borehole | · Drilling Equipping and | Eldama ravine | 2500 |
11 | Nato Community Borehole Wp | · Drilling Equipping and Civil Works | Mogotio | 2000 |
12 | Kabartonjo Referral hospital | · Drilling, Equipping and Civil works | Baringo North | 50 Outpatients per day and 24 bed capacity Inpatients |
13 | Civil works for Lokoiwo water project | · Pipe works | Baringo North | 1500 |
14 | Orinie Primary School Borehole Water Project | · Equipping and Civil Works | Eldama Ravine | 1000 |
15 | Equipping and civil works for Solian girls secondary school borehole | · Equipping and Civil Works | Eldama Ravine | 1200 |
16 | Equipping and civil works for Tandui community borehole | · Equipping and Civil works | Baringo Central | 2000 |
17 | Tolmo water project | · Construction of 100m3 masonry tank and distribution pipeline | Eldama Ravine | 1200 |
18 | Tinosiek borehole |
| Mogotio | 400 |
19 | Asenwe Communitty Borehole Wp |
| Mogotio | 1200 |
20 | Lemelok Community Borehole Wp |
| Baringo South | 1600 |
21 | Kupotwin Community Borehole Wp |
| Tiaty | 500 |
22 | Kaiso Community Borehole Wp |
| Baringo Central | 2500 |
22 | Kabergei Community Borehole Wp |
| Mogotio | 450 |
23 | Marram (Kacheptuyo) |
| Tiaty | 400 |
24 | Tenges Community Borehole Wp |
| Baringo Central | 3000 |
25 | Tabagon Community Borehole Wp |
| Baringo Central | 1480 |
26 | Rimo Community Borehole Wp |
| Baringo North | 800 |
27 | Sesoche Community Borehole Wp |
| Mogotio | 1300 |
28 | Kabarbaya Community Borehole Wp |
| Mogotio | 750 |
29 | Kapyemit Community Borehole Wp |
| Mogotio | 500 |
30 | Mosuro Community Borehole Wp |
| Baringo South | 400 |
31 | Mogotio Sub-county hospital |
| Mogotio | 70 Outpatients per day and 150 bed capacity Inpatients |
32 | Kipkaech(Ngetmoi) dispensary |
| Baringo Central | 50 Outpatients per day |
33 | Kotulpogh Bh |
| Tiaty | 300 |
34 | Kiplombe Secondary school borehole |
| Eldama Ravine | 600 |
35 | Maji Nyekundu Borehole |
| Mogotio | 2000 |
36 | KapKiamo Primary School Borehole |
| Baringo North | 1800 |
37 | Lelgel Primary School Borehole |
| Eldama Ravine | 2500 |
38 | Makoi water project |
| Mogotio | 3000 |
39 | Lolmolo-Kokorwonin |
| Eldama Ravine | 1000 |
|
|
|
|
|
This list includes 17 active projects.
No. | Project Name | Progress Status | Sub-County | Remarks |
1 | Solian-Kirobon LMC | 95% | Eldama Ravine | Pipeline/tank done; awaiting fittings |
2 | Kiplombe LMC | 95% | Eldama Ravine | 40.36km pipeline laid; testing ongoing |
3 | Kiptoim-Kures LMC | 98% | Mogotio | Awaiting branding and handover |
4 | Lotwala Borehole | 90% | Mogotio | Equipping/civil works complete |
5 | Kampi ya Samaki | 80% | Baringo South | UF and RO plant assembled on site |
6 | Bartulgel Community BH | 80% | Mogotio | Civil works complete; awaiting equipping |
7 | Mochongoi-Ngorobich LMC | 70% | Eldama Ravine | 18m steel tank tower complete |
8 | Akule Water Pan | 80% | Tiaty | Excavation done; sill/stone pitching pending |
9 | Kangoria Water Pan | 80% | Tiaty | Excavation done; sill pending |
10 | Kapkosom Water Project | 30% | Baringo South | Sump complete; tank construction ongoing |
11 | Kanjulul Water Pan | 30% | Eldama Ravine | Progress hindered by heavy rains |
12 | Chemogoch LMC | 25% | Mogotio | Slow progress due to cashflow issues |
13 | Kaboro Phase III | Ongoing | Baringo North | 30m³ tank and booster pump station |
14 | Kaptumo Phase III | Ongoing | Baringo Central | Solarization and 100m³ tank |
15 | Kaptiriony Secondary BH | Ongoing | Baringo Central | Drilling and test pumping phase |
Future Planning & Proposed Projects
- National Urban Phase II: Proposed projects include Kabartonjo Water Supply, Marigat Water Supply, Marigat Sewerage, and Mogotio Sewerage.
- Priority PPP Dams: Recommended for Public-Private Partnerships are Bergei Dam (6.4B), Narosura Dam (5.4B), and Saimo Soi Dam (10B).
- Studies: Feasibility studies are identified for the Chemolingot, Barwesa, and Kipsaraman water supply cluster and the Emining Sewerage project.